Current Progress:
- Posted roads, set to be in effect on Monday, February 26th, 2024 and run through Monday, May 6th, 2024
- Stockpiled approximately 200-300 tons of 1.5” stone in anticipation of mud season.
- Streamlined the application process for obtaining a permit to travel on a town posted road.
Upcoming Plans:
- Cuffing off ruts and ridges to smooth the 3/8” stone and washed sand (free of silt or mica) that is currently being distributed.
- Promptly filling mud holes and promptly addressing any other issues that arise.
- Employing the York rake to shift dirt and rocks, aiding in the drying process of the roads.
- Ensuring roads remain accessible for emergency vehicles.
How You Can Help:
- Whenever possible, avoid using gravel roads and opt for alternative routes.
- If you must use gravel roads, please adhere to the following guidelines:
- Avoid driving in ruts
- Opt for high points on the road
- Maintain a consistent speed
- Choose the driest lane available